Nasa's massive Moon rocket crawls out of factory to Florida launch pad

Space Launch System rocket is making its way to Florida launch pad

Powered by automated translation

Nasa's next-generation Moon rocket on Thursday began a highly anticipated, slow-motion journey out of its assembly plant en route to the launch pad in Florida for a final round of tests in the coming weeks that will determine how soon the spacecraft can fly.

Roll-out of the 32-storey Space Launch System (SLS) rocket with its Orion crew capsule perched on top marks a key milestone in US plans for renewed lunar exploration after years of setbacks and the public's first glimpse of a space vehicle more than a decade in development.

The process of moving the 5.75-million-tonne, towering SLS-Orion spacecraft out of its Vehicle Assembly Building at Nasa's Kennedy Space Centre in Cape Canaveral began at 5pm local time, weather permitting.

The megarocket — standing taller than the Statue of Liberty — will be slowly trundled to Launch Pad 39B on a giant crawler-transporter, creeping slowly along on a 6.5-km journey expected to take about 11 hours.

The spectacle, unfolding under clear skies, was carried live on Nasa Television and the space agency's website.

A band from the University of Central Florida played the US National Anthem as the roll-out began in front of throngs of employees and other onlookers gathered outside to watch the event.

The roll-out, paving the way for Nasa's uncrewed Artemis I mission around the Moon and back, was delayed last month by a series of technical hurdles the space agency said it has since resolved as teams readied the rocket for the launch pad.

Once secured at the pad, the SLS-Orion ship is to be prepared for a critical preflight test called a “wet dress rehearsal”, which will begin on April 3 and take about two days to complete.

Engineers plan to fully load the SLS core fuel tanks with supercooled liquid hydrogen and liquid oxygen propellant and conduct a simulated launch countdown — stopping seconds before the rocket's four R-25 engines would ignite — in a top-to-bottom evaluation of the entire system.

The outcome will determine when Nasa will attempt its first launch of the rocket and capsule combination, a mission designated Artemis I. The SLS-Orion constitutes the backbone of the Artemis programme, aimed at returning astronauts to the Moon and establishing a long-term lunar colony as a precursor to eventual human exploration of Mars.

The US Apollo programme sent six manned missions to the Moon from 1969 to 1972, the only crewed space flights yet to reach the lunar surface.

Artemis, named after the twin sister of Apollo in Greek mythology, seeks to land the first woman and the first person of colour on the Moon, among others.

But Nasa has several steps to take before it gets there, starting with a successful Artemis I flight, planned as an uncrewed journey 64,374 kilometres beyond the Moon and back. Nasa has said it was reviewing potential launch windows in April and May, but the timeline could slip depending on results of the dress rehearsal.

Eight or nine days after those tests are completed and the propellant is drained from the rocket, the ship will be rolled back to the assembly building to await the setting of a launch date.

Nasa announced in November that it would aim to achieve its first human lunar landing of Artemis as early as 2025, preceded at some unspecified date by a crewed Artemis flight around the Moon and back.

Both of those missions, and others to follow, will be flown to space by the SLS, which surpasses the Apollo-era Saturn V as the world's largest, most powerful launch vehicle, and the first exploration-class rocket built by Nasa for human space flight since Saturn V.

Updated: March 18, 2022, 6:46 AM